By James McVeigh, Construction Liberation. In construction since 2005, and in commercial roofing and cladding since 2016. BSc (Hons) Quantity Surveying.
You're a commercial subcontractor, you're flat out, and you run off a feeling that the jobs are doing fine. The bank balance looks OK. Then the final account comes in, or the year-end accounts, and a job you thought was making money made a loss instead.
Or it hasn't made as much as you'd hoped. You've got an inkling why, but you don't really know.
You're not alone. Most subcontractors we speak to have no real idea what their projects are making. Some don't report on project costs at all. Some do it one month, then get too busy to do it the next. And many simply don't have the time, or the tools, to get the visibility they need. We were exactly the same until we started using the Construction Liberation app. So the team keeps walking into problem projects with no idea how they're doing until it's too late to change anything.
This guide is about changing that. It explains CVR, job costing and WIP reports in plain terms, then covers the three stages of knowing your profit on every project: setting the job up before you start, knowing where it stands every month, and acting while you can still change the outcome.
We learned this the hard way, so you don't make the same losses
We've run a commercial roofing subcontractor since 2018. For years, we tried to get a live picture of our project financials, and couldn't.
We tried several platforms that promised the earth. Every one of them meant exporting the data by hand and reworking it into the format we needed. There was no way to track live budgets and no way to forecast profit. By the time a report was ready, it was out of date.
Only when we started using the Construction Liberation app did we get the financial visibility we needed.
Subcontractors have a unique problem. You could be running 20 projects at once, with a small team to manage the financials on all of them. Software built for main contractors, or general accounting software, isn't built for that. You need a system built for commercial subcontractors.
The real risk: you can be busy and still go broke
Turnover isn't profit. A loss you find at the final account can't be fixed, and one bad job could wipe out the profit from several good ones.
You need to know where a project is heading before you set foot on site, not after the fact, when it's too late. And your team needs the tools to plan each project's financials, rather than walking into the job on gut feel.
Running projects on gut feel isn't managing a business. It's hoping for the best.
Is every job on budget? CVR, job costing and WIP explained
The names change from country to country, but they all answer the same three questions. Is this job on budget? Is it making money? And will it still be making money when it's finished?
Job costing means tracking every cost on a job against the budget for that job: labour, materials, plant, subcontractors and preliminaries. It's the term used in accounting software such as Xero, and across the US, Canada, Australia and New Zealand. It's not the same as pricing a job. Pricing happens before you win the work. Job costing tells you how the job is actually performing once you're on site.
A CVR (cost value reconciliation) is the UK and Ireland's monthly check. It compares the value you've earned on a job (what you've applied for, including variations) with what it has cost you to date. The difference is your profit or loss on that job so far.
A WIP report or WIP schedule is the US, Canadian and Australian equivalent. It lists every live job, its contract value, costs to date, percentage complete and forecast profit. It also shows whether you're over-billed (you've invoiced ahead of the work done) or under-billed (you've done work you haven't invoiced yet).
WIP in your monthly accounts has a related meaning. It's the work you've carried out between your last valuation date and the end of the month, which hasn't been applied for yet. Without it, your accounts understate what you've earned that month.
What it's usually called where you work:
UK and Ireland: CVR (cost value reconciliation). Extra work is called variations or variation orders.
United States and Canada: WIP report or WIP schedule. Extra work is called change orders.
Australia: WIP report or job cost report. Extra work is called variations.
New Zealand: job cost report or WIP report. Extra work is called variations.
Whatever you call it, you need to see it at a glance, for your own sanity. Better still, your team needs to own it, so they drive the profit on each job and you don't have to. No more gut feel: just real numbers you can rely on.
Stage 1: Set every job up to make money before you start
Most of a job's profit is decided before anyone sets foot on site. If you don't know what the job should make, you can't tell whether it's on track.
Turn your tender into a budget you can measure against
Your tender already holds the numbers: labour, materials, plant, subcontractors and preliminaries. When the job is won, turn them into the job's budget, split into the same cost headings you'll track against.
If the budget only lives in the estimator's spreadsheet, the team running the job never sees it. Then nobody can say whether a cost is in line or over until it's too late.
Don't start a job without knowing your margin
Before you start, you should know the contract value, the payment terms, what's in scope and what isn't, and the margin you expect to make. Then forecast it: when the costs will land, and when the money should come in.
Once the job is running, the forecast shows where it's doing well and where it isn't. Is it the labour? The materials? Know where the losses and the errors are. Learn from the mistakes and the wins, job by job, and use them to improve the business and the team.
How the Construction Liberation app helps: Each job's budget and forecast are set up in the app, so the whole team works to the same numbers from day one. As costs come in, you see which cost headings are on track and which aren't.
Construction procurement: your biggest win on margin
Buying well is one of the biggest levers you have on margin, and one of the most neglected.
Where materials make up around 60% of your turnover, a 10% saving on materials could add about 6% to your net margin. Across a year's turnover, that could be huge.
Don't let orders go out without a thought for cost
Give your team the tools to find buying savings:
Buy against the budget. Every order should be checked against what was allowed for that item.
Use purchase orders. Committing costs without a purchase order means you don't know what you've spent until the invoice arrives.
Compare supplier quotes for every significant order, not just at tender.
Lock in prices and lead times, and check supplier payment terms against your own.
Track materials delivered, on site and stored off site, so you can claim them where your contract allows.
Plan the labour, don't just send it
Labour is the other big lever. Know where you could save on labour, and give your team the tools to plan it, rather than sending gangs to site and finding out at month end what it cost.
How the Construction Liberation app helps: Your team raises orders against the job's budget, so every order shows how it compares with the allowance. The app also helps plan the labour on each job, so you can see where the savings could be made before the costs are committed.
Stage 2: Know where every job stands, every month
Once the job is live, this is where job costing and construction cost management come in. The aim is simple: no surprises. Every month, on every job, you should know what you've earned, what it has cost, and where it's heading.
Stop waiting for the final account to find out you're over budget
Track two kinds of cost against the budget every month:
Actual costs: what's been invoiced and paid, such as supplier invoices, labour and plant hire.
Committed costs: what you've already agreed to spend but haven't been invoiced for yet, such as orders placed and subcontracts let.
If you only look at actual costs, a job can look on budget right up until the invoices land. Committed costs show the overspend while there's still time to act.
Every unrecorded variation or change order is margin you've given away
Variations, or variation orders (change orders in the US and Canada), are where margin quietly leaks out. The extra work gets done, nobody records the instruction, and months later at final account there's nothing to back it up.
Record every variation as it happens: the instruction, the photos and the value. Then it goes straight into your next application. Our Getting Paid guide covers recovering variations when they're disputed.
How the Construction Liberation app helps: Variations are tracked in the app. The customer instructs them digitally, and each instruction is added to your next application automatically. Your applications are evidenced without the extra admin, and it's hard for the main contractor to argue with a variation they instructed themselves. The evidence is there in black and white.
Your valuation and your costs have to tell the same story (your monthly CVR or WIP report)
Each month, compare the value you've earned on each job, including variations, with what it has cost you to date. That's your CVR, or your WIP report.
Two checks make it reliable:
Count the work since your valuation date. Costs keep coming in between the valuation date and the end of the month. Include the value of that work (your month-end WIP), and your accounts can be accurate every month, not just at year end.
Make sure your project accounts and your financial accounts match. What you've applied for should be picked up in your invoices. If they don't match, something has been missed.
That second check recently saved us £20,000. Our QS entered the wrong certified amount, which meant we under-invoiced on a project. The app flagged the mismatch, and we caught it. Before we had the app and its checks and balances, I dread to think how many times we'd made this mistake before.
Forecast your cost to complete and final margin from week one
A monthly CVR tells you where a job stands today. A forecast tells you where it's going to end up.
For each job, work out the cost to complete: what's left to spend to finish the job. Add it to the costs to date, compare the total with the final value you expect, including variations, and you have the forecast final margin. If that number is shrinking month by month, you know now, not at the final account.
The same remaining spend gives you each project's cash flow: spread it across the coming months to see when the money goes out. Without project cash flows, you won't know if you're heading into a disaster. Project cash flows also feed your business cash flow forecast, which our Financial Management guide covers.
Get your time back: let the system do the reconciliation
Doing all this by hand, on every job, every month, is exactly what gets dropped when site gets busy.
How the Construction Liberation app helps: Job costing, the monthly CVR or WIP report, month-end WIP and the checks between your applications and invoices are done automatically. Each job's remaining spend is spread across the coming months in a few clicks, so you get project cash flows without building a spreadsheet. You see where every job stands at a glance, and your team can own the numbers on their jobs.
Stage 3: Act while you can still change the outcome
Knowing a job is going wrong is only worth something if you act on it. The earlier you see it, the more options you have.
The warning signs that a job is going wrong
Watch for these each month:
The forecast final margin is shrinking, month after month.
Committed costs are running ahead of progress on site.
Labour hours are over the allowance for the work done.
Variations are being carried out but not instructed or valued.
Valuations are being cut, or certified late.
Preliminaries are running on because the programme has slipped.
One on its own might be nothing. Two or three together, and the job needs attention now.
Price and agree your variations before they become a dispute
An instructed variation that hasn't been priced or agreed is still a risk. Price it promptly, get it agreed in writing, and include it in your next application. The longer it sits, the harder it is to recover. Our Getting Paid guide covers what to do if it's disputed.
Bring an over-budget job back under control
When the numbers show a job going over, look at the costs you can still influence:
Labour: is the gang the right size for the work left? Is time being lost to access, sequencing or waiting on others? If the delay is someone else's, record it.
Plant: is anything on hire that isn't being used?
Preliminaries: if the programme has been extended by others, your extra preliminaries could be recoverable.
Materials: are there buying savings left on the remaining orders?
Feed every job's lessons back into your estimating
Every finished job tells you something about your rates, your outputs and your allowances. Compare the final costs with the tender, heading by heading, and feed what you learn back into your pricing. Learn from the wins as well as the losses. Your next tender will be sharper for it.
Retention: don't let it slip through the cracks
Retention is profit you've already earned. It's held back until practical completion and the end of the defects period, which is why it so often gets forgotten.
Track the retention held on every job, and claim it the day it falls due. Don't let months go by with it unclaimed. Our Getting Paid guide covers retention in more detail, including what could happen to it if a main contractor goes bust.
How the Construction Liberation app helps: Your retentions run on autopilot. The app tracks what's held on every job, shows when each release falls due, and makes sure no retention invoice gets missed.
Three steps from guessing to knowing what every job makes
Knowing your profit isn't about working harder. It's a process:
Set every job up before you start. Turn the tender into a budget, know your margin, and buy and plan against it.
Know where every job stands, every month. Track actual and committed costs, record every variation, run your CVR or WIP report, and forecast the final margin.
Act while you can still change the outcome. Spot the warning signs, get variations agreed, bring costs back under control, and feed the lessons into your next tender.
Stage 2 is where most subcontractors fall down. Not because they don't know what to do, but because there isn't the time to do it on 20 jobs every month. That's what our system was built for. It does the reconciliation for you, so the numbers are there even when site comes first.
From “busy but broke” to knowing your profit on every job
You know what every job is making, every month, without anyone building a spreadsheet. Your team owns the numbers on their jobs and drives the profit, so you don't have to. Variations are recorded and recovered. Your buying is sharper, and so is your next tender. And your accounts are right every month, not just at year end.
The alternative is the job you thought was making money turning out to be the one that sinks you.
Ready to know what every job is making?
Tell us how you track your job costs now, and we'll show you how our system gives you a live picture of every project.
Your questions, answered
What is job costing in construction? Job costing means tracking every cost on a job, such as labour, materials, plant, subcontractors and preliminaries, against the budget for that job. It shows whether each job is on budget and making money, rather than only seeing the profit for the business as a whole.
What is a CVR in construction? A CVR, or cost value reconciliation, is a monthly comparison of the value earned on a job (what you've applied for, including variations) with the costs to date. The difference shows the profit or loss on that job so far. It's the standard term in the UK and Ireland.
What is a WIP report in construction? A WIP (work in progress) report, or WIP schedule, lists every live job with its contract value, costs to date, percentage complete and forecast profit. It also shows whether each job is over-billed or under-billed. It's the standard report in the US, Canada and Australia.
What does WIP mean in a subcontractor's monthly accounts? It's the value of work carried out between your last valuation date and the end of the month, which hasn't been applied for yet. Including it means your monthly accounts show what you've actually earned, and keeps your gross margin from going up and down like a yo-yo.
How often should a subcontractor do a CVR? Monthly, in line with your valuations. Any less often, and a job could go over budget for months before anyone notices.
What's the difference between actual and committed costs? Actual costs have been invoiced. Committed costs are what you've already agreed to spend, such as orders placed and subcontracts let, but haven't been invoiced for yet. Tracking both shows an overspend before the invoices arrive.
How do you forecast a job's final margin? Work out the cost to complete, which is what's left to spend to finish the job, and add it to the costs to date. Compare that total with the final value you expect, including variations. The difference is the forecast final margin.
Can job costing work with Xero? Yes. Xero can track costs by project. The Construction Liberation app connects to Xero and adds what subcontractors need on top, such as budgets, committed costs, variations, CVRs and forecasting.
What is a good way to track job costs for a subcontractor? Set a budget for each job from the tender, track actual and committed costs against it every month, and record every variation as it happens. Spreadsheets can work for a few jobs, but with many live projects a system built for subcontractors saves time and catches mistakes.
Sources
This guide is based on our own experience of running a commercial subcontracting business. For more on getting paid, variations and retention, see our Getting Paid guide.