By James McVeigh, Construction Liberation. In construction since 2005, and in commercial roofing and cladding since 2016. BSc (Hons) Quantity Surveying.
You're a commercial subcontractor and you've done the work on site. The main contractor's client is happy. And the money still isn't in your account.
Your application has been cut unfairly. The retention from a job you finished two years ago is still sitting in someone else's bank, and nobody is answering your emails. And somebody in your business is spending hours every week chasing money that is rightfully yours.
It's frustrating, and it shouldn't be this way. The main contractor who causes most of the problems shouldn't get to decide whether you get paid, when you get paid, and how much.
This guide is about changing that. It covers the three stages of making sure you get paid what you're owed: before you sign the contract, while you're on site, and when you have to escalate.
We learned this the hard way, so you don't face the losses we did
We've run a commercial roofing subcontractor since 2018. Most of what's in this guide, we learned by getting it wrong first.
We've had customers go insolvent and never been paid for work we'd already carried out.
We've had money unfairly deducted from our accounts. Some of it we got back. Some of it we never saw again.
We've been to adjudication and won, but still lost. We were awarded everything we expected, and the main contractor even had to pick up the adjudicator's fees because of how they'd behaved. More on that in Stage 3.
Every one of those lessons cost us money. They're now built into how we work, and into the Construction Liberation system we built to run our own commercial subcontracting business. This guide shares each lesson so you can avoid the mistakes and get on top of your bank balance.
As the old saying goes, cash is king. When it isn't coming in, it affects everything: whether you can pay your suppliers on time, your relationships with them, and whether you have to borrow to cover the gap. It affects your mental health too. The stress of wondering whether you can pay your bills can make you question whether running a subcontracting business is worth it at all.
The real risk of taking no action is it costs you your business
Customers keep paying way beyond terms, because chasing takes too long and the process isn't followed. Deductions go unchallenged and become a habit. Retention gets forgotten. And you keep being underpaid for work you've already delivered.
Worst case, it's the business. Cash flow is what kills construction companies, and it's usually not the work that goes wrong.
Make the payment rules work for you
The names change from country to country, but the payment cycle on most subcontracts follows the same four steps:
You claim. You submit an application or payment claim for the work done to date, usually monthly.
They respond. The main contractor says what they intend to pay and, if it's less than you claimed, why.
Payment falls due. Your contract, or the law where you're working, sets when the money must be paid.
You're paid, or you act. If the money doesn't arrive, there may be a set route to recover it.
Most of the countries we work in have construction payment laws that may protect you, even where your subcontract says something different. Here's how the terms and routes compare:
UK: you submit a payment application, and the main contractor responds with a payment notice or a pay less notice. The main law is the Housing Grants, Construction and Regeneration Act 1996, as amended (the "Construction Act"). If you're not paid, the routes are suspension and adjudication.
Ireland: you submit a payment claim notice, and the response is a response notice. The main law is the Construction Contracts Act 2013. The routes are suspension and adjudication.
New Zealand: you submit a payment claim, and the response is a payment schedule. The main law is the Construction Contracts Act 2002. The routes are suspension and adjudication.
Australia: you submit a payment claim, and the response is a payment schedule. Each state has its own Security of Payment Act. The routes are suspension and adjudication, with rules that vary by state.
United States: you submit a pay application, and the response depends on your contract. Prompt payment laws vary by state. The routes include mechanic's liens and claims on payment bonds, which also vary by state.
Canada: you submit a progress invoice or proper invoice, and some provinces require a notice of non-payment. Prompt payment laws vary by province. The routes include holdback and lien rights, and adjudication in some provinces, such as Ontario.
Rules in Australia, the US and Canada vary by state or province, so always check the rules where your project is.
This guide is general information, not legal advice. What you can do depends on your contract and the law where the work is carried out.
Stage 1: Win the payment battle before you sign the contract
Most payment problems are decided before the first operative sets foot on site. Who you work for, and the terms you accept, set the odds long before you submit your first application.
The best job to lose is the one that would never have paid anyway
Not every customer is worth winning. There's no point working for someone who can't pay their bills, however good the job looks.
Credit check your customers at tender stage, before you spend days pricing. If a main contractor has a credit limit of zero and the job is worth a million, that tells you most of what you need to know. Your estimator's time could be better spent elsewhere.
Then keep checking. A customer's position can change a lot between the tender and the final account, so check again at order, and regularly while you're on site. Most credit-checking services can alert you automatically when a customer's financial position changes. Use that feature.
We've declined to tender for main contractors who later went into administration. Each of those was a job we were glad to lose. We've also gone ahead with jobs we knew we should have turned down, and come up short, without being paid what we were owed.
See trouble coming before your customer stops paying
A credit check shows you a customer's position based on what's been filed and reported. Credit insurance could give you a much wider view.
A credit insurer sees how a customer pays across all of its policyholders, including payments that have been missed. That's a live picture no single credit check can match, and the insurer may refuse or reduce cover on customers it's worried about. That alone can be a useful early warning. And if a covered customer doesn't pay, the policy may pay out a large part of what you're owed.
It won't suit every business or every customer, but it's worth getting a quote to see if it's right for your business.
The small print that could leave you unpaid: pay when paid, set-off and other clauses to watch
Read the subcontract before you sign it, and push back on the terms that put your money at risk. These are the common culprits:
Pay when paid, or pay if paid. The main contractor doesn't have to pay you until, or unless, their client pays them. Some countries ban these clauses in most cases, but there may be exceptions, such as when the client becomes insolvent.
Long notice periods before you can stop work. A 30-day notice period means you could be working unpaid for a month after the money should have arrived.
Long payment terms. 60 days or more is effectively an interest-free loan to the main contractor.
Payment by cheque. It's slow, and it adds days to every payment.
No payment for materials on site. You've bought them and delivered them, but you can't claim them until they're installed.
Cross-contract set-off. The main contractor can deduct money they claim on one job from what they owe you on another. One dispute could then hold up your payments across every project you have with them.
You'll never have more bargaining power than before you sign
Once the contract is signed, your leverage drops sharply. Before it's signed, you could ask for:
Lower retention, or a cap on the total amount held
Capped liability, so one problem can't wipe out the profit on the whole job
Shorter payment terms
Payment for materials on site, and for materials stored off site where they're clearly marked as yours
Pick your battles, though. In our experience, heavy negotiation can sour the relationship from the start. We keep our amendments to a minimum and focus on the points that matter most. The aim is to get them agreed without a long back-and-forth, while still giving yourself the best chance of getting paid.
How the Construction Liberation app helps: Your team sees each customer's credit score and insured limit in the CRM, so everyone knows who is creditworthy. When a job is won, the handover section records the key contract terms, credit terms, risks and leverage points in one place. The whole team knows where they stand and what to do, so nothing gets missed.
Stage 2: From chasing payments to getting paid on time
Once the job is live, getting paid comes down to three things: knowing exactly what you're owed, making claims that stand up, and chasing every time, without fail.
Stop guessing who owes you money
If you can't say right now who owes you what, and how overdue it is, you can't chase it properly. Too often that picture only exists once somebody has spent half a day pulling it together from spreadsheets, and it's out of date the next morning.
You need a live picture of your accounts: every application, every payment received, every amount outstanding and every retention held, project by project.
How the Construction Liberation app helps: It shows who has and hasn't paid, on every project, live, with no building the picture by hand first. Your team can add comments to each invoice, so there's a running record of what's been chased and when. And a weekly email shows everyone who has and hasn't paid, so they can decide whether to deliver materials, send labour, or prioritise the projects that are paying.
Give them no reason to cut your payment application
The easiest application for a main contractor to cut is one with no evidence behind it. Make every claim easy to approve and hard to argue with:
Attach the evidence: measured quantities, photos, signed day sheets and delivery notes.
Keep contemporaneous records: site diaries, issue reports and customer reports, written at the time. Record photos, descriptions, conversations and the weather, so you can back up every claim.
Get every instruction for extra work in writing before you start it. An email that doesn't quite approve the change could leave you with nothing to back it up months later.
Price variations promptly and keep a running log, so nothing gets forgotten at final account.
Submit on time, every time, in the format your contract asks for.
How the Construction Liberation app helps: Your payment applications are evidenced automatically. Variations are built in the app and sent to the customer, who approves them with a digital signature by clicking a link in an email. Approved variations are added to your next application automatically. Site diaries, customer reports, issue reports and photos are all captured in the app too, in one timeline for each project.
Once the deductions start, you could already be on a losing streak
We've had main contractors take money out of our accounts that they had no right to take. Some of it we recovered. Some of it we never did.
What we learned is that the first unfair deduction is often the start of a pattern, not a one-off. Once a main contractor sees that a deduction goes unchallenged, the next one tends to follow. So challenge every deduction in writing, straight away, and ask for the breakdown behind it. In the UK, check whether a valid pay less notice was issued on time. In Australia and New Zealand, check the payment schedule. If the procedure wasn't followed, the deduction may not stand.
We've seen how quickly a difficult customer can drag you down that slope. The moment it starts, evidence everything: photos, reports and issues. You need the whole project in a documented timeline, and our app keeps that timeline for you.
Stop chasing when you remember. Start chasing like clockwork
Chasing works when it's a process, not a mood. Decide the steps once, and follow them on every invoice:
Before it's due: a friendly check that the application has been received and approved.
On the due date: a reminder that payment falls due today.
A few days overdue: a firmer chase, copied to someone more senior.
Further overdue: a formal letter setting out what's owed and what happens next.
The point is consistency. When chasing depends on someone remembering, or finding the time, invoices slip and customers learn they can pay late.
Get your time back: let the system chase for you
The more of your chasing you can automate, the less it depends on someone finding the time.
How the Construction Liberation app helps: Chase emails are drafted for you from standard templates at the right time. You pick the customer, decide the final wording and choose when to send. Each email is signed off by the person sending it, and replies go straight back to them. Every customer gets the same process, every time, and a timeline shows exactly where each invoice is up to.
Serve your notices early, or you could end up working for free
Most subcontracts, and the payment laws in many countries, may give you the right to suspend work if you're not paid. But that right usually depends on following the procedure exactly: the right notice, in the right form, at the right time.
Miss a step and you could be forced to keep working on site, unpaid, because you didn't follow the contract procedure. Serve your notices as soon as you're entitled to, even if you hope you'll never need them. If the money then arrives, nothing is lost. If it doesn't, your right to stop is already protected.
How the Construction Liberation app helps: It prompts each step of the notice procedure at the right time, so your right to suspend is protected without anyone needing to remember the dates. You can also flag high-risk customers and change the process for them, for example going straight to withdrawing from site without the intermediate steps.
Stage 3: When they still won't pay, you're not out of options
Sometimes you do everything right and the money still doesn't come. This is where the groundwork from Stages 1 and 2 pays off, because every option below is stronger if your claims are evidenced and your notices have been served.
Work through the options in order. Each step costs more time, money and goodwill than the one before.
You hold more cards than you think
You may be holding things the main contractor, or their client, needs:
Warranties, such as manufacturer-backed guarantees
Operation and maintenance manuals, and other handover documents
Further works on the same project or other projects
Where your contract allows it, holding these back until you're paid could be a powerful incentive. Check your contract first: withholding something you're obliged to provide could put you in breach.
We've seen this work even after a main contractor collapsed. We were owed £100,000 on a project when the main contractor went insolvent. When the client took the project on, we recovered 80% of that, because the client needed our roofing warranty. We called our supplier and explained the situation, and they agreed not to supply materials for that project to anyone else. The client's choice was to use us, or be left with an unwarranted roof.
When your chasing is ignored, a third party gets their attention
When your own chasing stops working, a letter from a third party shows the main contractor that the matter has been escalated.
Some credit-checking services, such as Top Service in the UK, offer this as part of their service: first a warning letter, then a letter giving seven days' notice before action. A letter from a commercial or legal consultant can carry even more weight. Either way, it's often enough to move your invoice to the top of the pile.
Down tools without putting yourself in breach
If you served your notices on time in Stage 2, you may be entitled to suspend work until you're paid. In some countries you may also be able to recover the costs of the suspension and get extra time to finish.
Suspending is a big step, and doing it without following the procedure exactly could put you in breach of contract. Take advice if you're unsure.
Construction adjudication: you can win and still lose
In many of the countries we work in, the law may give you the right to take a payment dispute to adjudication: a fast-track process where an independent adjudicator decides the dispute in weeks rather than years. In the US and Canada, lien rights and payment bond claims play a similar role.
We've been to adjudication. We were awarded everything we thought we'd get. The adjudicator even ordered the main contractor to pay the adjudicator's fees, because of how they'd behaved.
We still lost out.
We got what we were owed. But once we added up our own time and what it cost the business, the legal fees we didn't recover, and the cost of finance to replace the cash while we waited, we only broke even. And the work we didn't win while we were tied up in it was a cost nobody will ever pay back.
That's the most important lesson in this guide. Adjudication is a valuable right, and sometimes it's the only way to get what you're owed. If you need it, appoint a legal or commercial consultant who knows construction disputes. But the real wins happen in Stages 1 and 2, before a dispute ever starts.
How the Construction Liberation app helps: If it does come to a dispute, your applications, evidence, variations, notices and chase history are already in one place. That could save days of pulling a claim together.
Retention in construction: your profit, so don't leave it behind
Retention (called retainage in the US and holdback in Canada) is your money, earned for work you've already done, held back by the main contractor as security against defects. It's usually released in two halves: one at practical completion, the other at the end of the defects period, often a year or more later.
That's exactly why it gets lost. By the time it's due, the job is long finished, the people who ran it have moved on, and nobody is watching the dates.
Retention needs attention at every stage:
Before you sign: negotiate a lower percentage, a cap on the total held, or a retention bond instead of cash retention.
While you're on site: track the amount held on every application, and record the practical completion date as soon as it's confirmed.
When it falls due: chase it on the day it's due, using the same process as any other invoice. Diarise the end of the defects period on the day the job finishes.
When the main contractor goes bust, your retention could go with it
If a main contractor becomes insolvent while holding your retention, you may become an unsecured creditor for that money, unless it's protected by law or by your contract. In many cases, unsecured creditors recover little or nothing.
The protection you have depends heavily on where you're working:
UK: there's no general legal requirement for retention to be held in trust, unless your contract says so.
Ireland: there's no general legal requirement for retention to be held in trust, unless your contract says so.
New Zealand: retention money must be held on trust under the Construction Contracts Act 2002.
Australia: retention trust rules apply in some states, often only above a contract value threshold.
United States: retainage is often limited by state law, and the rules on its release vary by state.
Canada: a statutory holdback is retained under each province's construction or lien legislation, with set rules for release.
How the Construction Liberation app helps: Retention is tracked automatically on every project, with release dates in view, and a warning banner tells you when a retention is due for release. The app also checks what you've applied for against what you've invoiced, so your accounts always match. Those checks recently saved us £20,000, when an incorrect previously certified figure meant we had under-invoiced on a project.
Three steps from chasing money to cash in the bank
Getting paid isn't luck, and it isn't about who shouts loudest. It's a process:
Protect yourself before you sign. Credit check the customer, read the contract, and negotiate the terms that put your money at risk.
Run the same process on every job. Keep a live picture of what you're owed, make claims that stand up, chase on time, and serve your notices early.
Escalate on time when it goes wrong. Use your leverage, then third-party letters, then suspension, then adjudication, in that order.
Stage 2 is where most subcontractors fall down. Not because they don't know what to do, but because there physically isn't the time to do it on every invoice, every month. That's what our system was built for. It runs Stage 2 for you and keeps Stage 3 on track, so the process happens even when site comes first.
From underpaid to the subcontractor who always has cash in the bank
You know exactly who owes you what, on every project, right now. Your applications are evidenced. Your chase emails are drafted for you, and you decide the wording and when they go. Deductions are challenged straight away. Retention comes back on time. And the hours your team used to spend chasing go back into the work that makes the money.
Ready to get paid what you're owed?
Tell us where the money gets stuck in your business, and we'll show you how our system gets you paid faster.
Your questions, answered
What can I do if a main contractor won't pay me? Start by checking your contract and the payment law where the work is. Then follow a set escalation: chase in writing, use any leverage your contract allows, send a third-party letter, consider suspending work if you've served the right notices, and if needed, take advice on adjudication or the equivalent route in your country.
Can a main contractor deduct money from my payment? In many countries, the main contractor may only pay less than you claimed if they tell you in the right way and at the right time, with their reasons. Challenge any deduction in writing straight away and ask for the breakdown. Unchallenged deductions tend to repeat.
How long does a main contractor have to pay a subcontractor? It depends on your contract and the law where you're working. Some countries set default payment periods where the contract doesn't, and some limit how long payment terms can be. Check your subcontract before you sign, and negotiate shorter terms if you can.
Can a main contractor hold my retention? Yes, if your contract allows it, but usually only until the release points set in the contract, typically practical completion and the end of the defects period. In some countries the law also controls how retention must be held. Track your release dates and chase on the day they fall due.
What happens to my money if the main contractor goes into administration? You may become an unsecured creditor for what you're owed, including retention, unless it's protected by law or your contract. That's why credit checking before you tender, and throughout the job, matters so much. If it does happen, think about what leverage you have, and whether you could get the client or the project's funder to pay your outstanding invoices.
Is adjudication worth it? It can be. It's faster and usually cheaper than going to court, and it may be the only way to recover a large sum. But even a win could cost you in legal fees, time and lost opportunities, so the best approach is to prevent disputes in the first place.
What is a pay less notice? In the UK, a pay less notice is the notice a main contractor must give if they intend to pay less than the amount due on your application. It must usually say what they will pay and how they worked it out, and be given within the time your contract or the Construction Act sets. If it isn't, you may be entitled to the full amount.
What is retainage? Retainage is the US term for retention: a percentage of each payment held back until the work is complete. Many states limit how much can be held and set rules for when it must be released. In Canada, the equivalent is called holdback.
This guide is general information, not legal advice. Your rights depend on your contract and the law where the work is carried out. Take professional advice on your own situation.
Sources
UK: Housing Grants, Construction and Regeneration Act 1996, Part II, as amended by the Local Democracy, Economic Development and Construction Act 2009
Ireland: Construction Contracts Act 2013
New Zealand: Construction Contracts Act 2002
Australia: Security of Payment legislation in each state and territory
United States: state prompt payment and mechanic's lien laws
Canada: provincial prompt payment, construction and lien legislation, including Ontario's Construction Act